chore: remove phase 7 (Metronome Implementation)
This commit is contained in:
parent
73ac37b97b
commit
aa129fed56
|
|
@ -22,7 +22,6 @@ Decimal phases appear between their surrounding integers in numeric order.
|
|||
- [x] **Phase 4: JamTrack Research & Design** - Explore legacy jQuery/CoffeeScript implementation, design React patterns
|
||||
- [x] **Phase 5: JamTrack Implementation** - Build JamTrack player with mixdown selection and controls
|
||||
- [ ] **Phase 6: Metronome Research & Design** - Explore legacy implementation, design React patterns
|
||||
- [ ] **Phase 7: Metronome Implementation** - Build metronome with tempo/sound/cricket configuration
|
||||
|
||||
## Phase Details
|
||||
|
||||
|
|
@ -89,19 +88,10 @@ Plans:
|
|||
Plans:
|
||||
- [ ] TBD during phase planning
|
||||
|
||||
### Phase 7: Metronome Implementation
|
||||
**Goal**: Build metronome with tempo/sound/cricket configuration and start/stop controls
|
||||
**Depends on**: Phase 6
|
||||
**Research**: Unlikely (following patterns established in Phase 6)
|
||||
**Plans**: TBD
|
||||
|
||||
Plans:
|
||||
- [ ] TBD during phase planning
|
||||
|
||||
## Progress
|
||||
|
||||
**Execution Order:**
|
||||
Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7
|
||||
Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6
|
||||
|
||||
| Phase | Plans Complete | Status | Completed |
|
||||
|-------|----------------|--------|-----------|
|
||||
|
|
@ -111,4 +101,3 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7
|
|||
| 4. JamTrack Research & Design | 2/2 | Complete | 2026-01-14 |
|
||||
| 5. JamTrack Implementation | 5/5 | Complete | 2026-01-14 |
|
||||
| 6. Metronome Research & Design | 0/TBD | Not started | - |
|
||||
| 7. Metronome Implementation | 0/TBD | Not started | - |
|
||||
|
|
|
|||
|
|
@ -9,7 +9,7 @@ See: .planning/PROJECT.md (updated 2026-01-13)
|
|||
|
||||
## Current Position
|
||||
|
||||
Phase: 5 of 7 (JamTrack Implementation) - COMPLETE
|
||||
Phase: 5 of 6 (JamTrack Implementation) - COMPLETE
|
||||
Plan: 5 of 5 in current phase
|
||||
Status: Phase Complete
|
||||
Last activity: 2026-01-14 — Completed Phase 5 Plan 5 (Error Handling & Final UAT)
|
||||
|
|
|
|||